Hidden Groves diary

2019–2021

September 2019 -- We buy Hidden Groves

Lot Warming Party

September 2019 -- We buy Hidden Groves

December 2019 -- We first submit building plans

2020 -- We planted the orchard, the pineapple guava circle, and much more.

First nectarine in July 2020

2020 -- We planted the orchard, the pineapple guava circle, and much more.

2020 -- we build several sheds and the first greenhouse

2020 -- we build several sheds and the first greenhouse2020 -- we build several sheds and the first greenhouse2020 -- we build several sheds and the first greenhouse

April 2021 -- We get building permits

April 2021 -- We get building permitsApril 2021 -- We get building permitsApril 2021 -- We get building permitsApril 2021 -- We get building permitsApril 2021 -- We get building permits

Krista finishes Soul of the Sun. April 2021

Krista finishes Soul of the Sun. April 2021

cottage foundation April 2021

A crew built the forms and had the concrete poured. Now we are taking apart the forms. Lumber costs have tripled since last year so we will reuse as much of it as possible.

cottage foundation April 2021

June 7, 2021: Passed Subfloor Inspection

Sill plate, floor joists, and underfloor wiring, plumbing, and drain lines done.

July 1: Starting to Build Walls

Lumber is so expensive this year!

June 7, 2021: Passed Subfloor InspectionJune 7, 2021: Passed Subfloor Inspection

July 14, 2021: Walls

It's starting to look like a house!

July 14, 2021: Walls

July 26, 2021: Rafters

Frankie is painting the fascia boards for the outside of the roof.

July 28, 2021: Roof decking on.

There's sort of an indoors now.

July 26, 2021: RaftersJuly 26, 2021: Rafters

August 9, 2021: Front Porch

And now lumber prices start to come down...

August 9, 2021: Front Porch

August 11: Starting Windows

The cottage is 640 square feet and has 18 windows. The house we are renting now is 1400 square feet and has 8.

August 12: Doors

Maybe we thought there was an indoors before, but now we mean it.

August 11: Starting WindowsAugust 11: Starting Windows

August 17, 2021: Loft above shower and shower vent fan

The loft is exactly 6 feet long, and now we realize that if we had made it 4 inches bigger, we could've squeezed a mattress up there. Oops!

August 17, 2021: Loft above shower and shower vent fan

August 19: Plumbing

We have run water lines to the bathroom, kitchen, and outdoor spigots, as well as all the drains and vents.

August 26: Started Electrical

We have begun putting in some of the wiring and receptacles. We bought a 400 Amp circuit breaker panel, but it won't be installed for weeks.

August 19: PlumbingAugust 19: Plumbing

September 2, 2021: We have roof

It's only September, and we're pretty much ready for rain. Our roof sheds water. It's supposed to, anyway -- we haven't tested it. Next up, stucco and electricity. Our mini-split heat pump is on backorder until October 15, so I hope we'll have juice by then.

September 2, 2021: We have roof

September 9: Stucco Lath

We passed the stucco lath inspection. We did a 1-coat job, so we'd get another inch of styrofoam insulation on the outside.

September 18: Stucco done

The house is now weatherproof. Or it will be as soon as we have doorknobs, I guess. Next up: Doorknobs! And electrical panel.

September 9: Stucco LathSeptember 9: Stucco Lath

September 21: Temporary Stairs

Joe failed the cinder block challenge, so we made some temporary steps out front. Eventually we plan a terrace of some kind.

September 28: Doorknobs

We just learned that when you get deadbolts at the same time, you can look at the key number to make sure the same key opens all of them, so our front and back doors use the same key. Handy!

September 21: Temporary StairsSeptember 21: Temporary Stairs

October 7, 2021: Circuit Breaker Panel

This is Jon, our electrician, after installing our 400 Amp Circuit Breaker Panel.

We still haven't dug the trench that goes from the telephone pole to the cottage (about 200 feet, 3 feet deep), but we're hoping in the next week or so.

After the trench, we'll bury the conduit and get an inspection, then about 2-3 weeks to get the power company to pull the wires and give us juice.

With electricity everything will change!

October 7, 2021: Circuit Breaker Panel

October 22, 2021: Electrical Conduit

We had to dig a 200 foot long 40 inch deep six inch wide trench (involving renting a giant trencher) to lay in 3 inch conduit from the electric pole to the cottage.

October 23: Rain troubles

After laying our conduit, we had an improbable and unseasonable three inches of rain that flooded our trench -- making the conduit float up out of it while mud sluiced underneath. Poop! Fixing that caused some delay. Finally got our electric tags on November 4.

October 22, 2021: Electrical ConduitOctober 22, 2021: Electrical Conduit

November 15, 2021: Electrical Meter

Finally got our trenches and conduit and wires and whatnot sorted out, and SMUD has hooked us up to power. Yay! Next we'll have to install all the circuit breakers in the panel and start getting the power on inside.

November 20: First wall

We built one side of one interior wall so that when we turn on the power we have a place to plug things in. It's unfinished on the other side so we can still get inspections.

November 15, 2021: Electrical MeterNovember 15, 2021: Electrical Meter

December 5: Hot mopped shower

We had the professionals tar and feather the bottom of the shower stall.

December 20: Rainbows at noon

We have some refractive film on the big kitchen window that sprays pretty colors on our one wall at noon.

December 5: Hot mopped showerDecember 5: Hot mopped shower