2026

September

Top floor of the Front House making progress. On schedule to have the roof on before rainy season.

September 2026 at Hidden Groves

August

Bottom floor of the Front House mostly framed. Our mission is to have the roof on before rainy season.

August 2026 at Hidden Groves

July

Lumber delivery for most of the bottom floor.

July 2026 at Hidden Groves

June

Crawlspace has sewer, electrical, water, insulation, joists—ready for the floor.

June 2026 at Hidden Groves

May

We built the footings, piers, and stem walls for the Front House.

May 2026 at Hidden Groves

April

We dug footings for the Front House, but rain filled them up and stalled our hopes for an early spring start. Oops!

April 2026 at Hidden Groves

March

We built an outdoor table that says “HG” for Hidden Groves, though it doubles as a Jack in the Box icon.

March 2026 at Hidden Groves

February

We snuck out of the brutal California winter for a vacation in Kauai, Oahu, and Hawai‘i.

February 2026 at Hidden Groves

January

We installed an enormous TV in the Movie Pit in the Back House.

January 2026 at Hidden Groves